Reason for the Callout
An Ang Mo Kio HDB water heater was experiencing leaks and rust, making it unreliable. To restore consistent hot water, the owner opted for a replacement with the same brand and engaged Homeone for a safe, compliant installation. With Homeone’s expertise, the HDB now has a properly installed and dependable water heating system.
HDB
Ang Mo Kio HDB Water Heater: Joven JH25 Replacement at Blk 617 Ang Mo Kio Ave 4
The ageing Joven JH25 water heater was due for replacement. We installed a new Joven JSH25, ensuring a safe and reliable hot water system. The installation of the Ang Mo Kio HDB water heater was completed with all necessary safety upgrades, and a PUB Certificate was issued for full compliance.
Before: Joven JH25
After: Joven JSH25
Date Of Replacement: 16 Aug 2024
Project Location: 617 Ang Mo Kio Ave 4

Before Replacement:

The existing Joven JH25 had exceeded its lifespan and was no longer functioning properly. It also lacked essential safety features, such as a double check valve to prevent backflow and electrical bonding to reduce the risk of electrocution.
After Replacement:

A new Joven JSH25 was installed at the same location, this time with all required safety enhancements, including a double check valve for anti-backflow protection and equipotential bonding for electrical safety. The installation complies fully with PUB and regulatory standards and is covered by a one (1) year workmanship warranty from Homeone, in addition to the manufacturer’s warranty for the unit.
Inspection Findings 
- Visible tank body corrosion and water leakage
- Intermittent hot water output
- No double check valve, and no drain pipe
- No electrical bonding
Components Replaced for PUB Submission Compliance:
- Joven JSH25 electric vertical water heater
- Anti-vacuum valve at hot outlet (required for vertical tanks)
- PUB-approved double-check valve on cold inlet
- Stainless steel inlet and outlet piping (≤1m)
- Stop cock / control valve for maintenance shut-off
- Compression fittings, elbows, brackets, and wall anchors
- Electrical bonding cable to the nearby metal pipe for safety
Replacement work scope:
- Isolated power and water supply
- Removed the existing Joven JH25 and cleared the installation area
- Inspected the wall, pipe layout, and drainage route
- Installed the new Joven JSH25 in the same vertical configuration
- Fitted anti-vacuum valve per Rheem specifications
- Installed PUB-compliant double-check valve and stop cock
- Replaced old copper pipes with stainless steel pipework within 1 metre
- Connected and tested electrical bonding to ensure proper grounding
- Performed full leak testing and pressure checks
- Submitted all documentation for PUB review and issued a valid PUB Certificate


Our PUB Licensed Plumber has endorsed that the work is done in accordance with the conditions stated below:
- All water service installations must be in accordance with the Public Utilities (Water Supply) Regulations, Singapore Standards 636 for Water Services, and all other relevant statutory requirements.
- The proposed works shall not adversely affect the existing water supply reticulation system.
- The proposed water storage heater is installed in accordance with the specifications and requirements of the manufacturer.
- The installation of double-check valves is safe and effective in preventing backflow and the back-siphonage of water from the storage water heater through the heater inlet pipe, and will be safe for use.
Conclusion:
This project at Ang Mo Kio shows that even a same-model water heater replacement requires full attention to safety and compliance. Our team installed a new Joven JSH25 with all required upgrades and issued a valid PUB Certificate, ensuring the system is safe, traceable, and fully compliant with Singapore’s plumbing and electrical regulations.